Travel update
What’s closed this Christmas.
Last checked 21 November 2026
The big railway closures over Christmas and New Year 2026/27, with dates and where each comes from.
Checked against Network Rail’s Christmas and New Year engineering works page on 21 November 2026. Plans change. Check your operator and the National Rail journey planner before you travel.
Most routes stay open, but Network Rail says trains will not run on most routes in England on Christmas Day and Boxing Day. It lists these larger closures.
The closures
London Paddington
Closed from Christmas Day. Services begin returning from New Year’s Eve.
Heathrow Express and Elizabeth line trains link Paddington and Heathrow again from 31 December. The Elizabeth line does not run further west than Paddington until 4 January 2027. Great Western Railway trains cannot reach Paddington until Monday 4 January 2027: its long-distance services start and finish at Reading, and some divert to London Euston. The station stays open for toilets and other facilities.
Birmingham New Street
Closed from Christmas Eve until the start of service on Tuesday 29 December.
Part of a three-year project to replace overhead power supplies. The station stays open for toilets and other facilities.
Redhill (Brighton Main Line)
Closed from 20 December until the early hours of Monday 4 January 2027.
New track and points. Buses replace trains from Reigate and intermediate stations from Earlswood to Purley on the Brighton Main Line. Check your own journey with your operator, because the stations around the works differ.
Great Eastern Main Line (Forest Gate)
Closed for 10 days from Christmas Day, until the early hours of Monday 4 January 2027.
Track replacement at Forest Gate in east London. No Greater Anglia or Elizabeth line trains run through the area. Liverpool Street to Cambridge via Stansted Airport is not affected. Network Rail’s page does not state replacement transport, and some operator notices give slightly different dates, so check Greater Anglia and the Elizabeth line.
Huddersfield
Disrupted from Christmas Day until the morning of 1 February 2027.
The final phase of the Huddersfield station transformation, part of the TransPennine Route Upgrade. This is disruption rather than a full closure.
Source for every date above: Network Rail, Christmas and New Year engineering works, read 21 November 2026. Network Rail’s page did not list any other closures at that time. Its journey planners are up to date through 4 January 2027.
What to check before you travel
- Search your exact journey in the National Rail journey planner, for the day and the time. Network Rail says planners are up to date through 4 January 2027.
- Look at your train operator’s own Christmas page. They publish the replacement bus details and any changes to the days either side.
- Check the start and the end of each closure. Several finish in the early hours of Monday 4 January, not on Sunday night.
- Allow extra time if a bus replaces your train, and check where the buses leave from.
- Look again on the day. Engineering works can overrun.
How LiveTrains Pro helps
LiveTrains Pro is not a journey planner and does not list planned closures, so use the sources above for that. Once you know which trains are running:
- Pin your train. It follows you on the Lock Screen, in the Dynamic Island and on Apple Watch.
- See the predicted platform early. At supported stations the app shows it before the station board does. It is usually right, but it can change.
- If a train is cancelled, Rescue lists later direct trains and lets you switch to one with “Track this instead”.
Free on iPhone and Apple Watch, with ads. One-off £4.99 Remove Ads purchase. No account needed.